Two Phase Smart Meter Installation

Wire a Qube two-phase meter on R and B only. RS, RL, BS, BL, and neutral, with YS and YL left open as the line diagram shows.

Qube Team · · 3 min read · 20 minutes · Medium

Qube two phase line diagram with R and B connected and the Y terminals crossed out

Use this guide when the Qube meter sees R and B only. The line diagram crosses out the yellow terminals. A shop, a floor, or a room pair on two phases follows this drawing. A supply that also has Y follows the three-phase guide instead.

The same terminals are on the interactive wiring guide.

Before anyone opens the cover

Switch off both phases and the neutral at the distribution box. Test R, B, and neutral and confirm they are dead. Two live phases are easy to miss if you only test one colour.

S on a terminal mark means source, the input from the MCB. L means load, the output. N is neutral. R is red. B is blue. Y is yellow, and on this install it stays unused.

Terminals

MarkWhat lands there
RSR source, from the R MCB.
RLR load, toward that circuit.
YSEmpty. Crossed out on the diagram.
YLEmpty. Crossed out on the diagram.
BSB source, from the B MCB.
BLB load, toward that circuit.
NSNeutral source. Incoming neutrals join here.
NLNeutral load, out to the rooms or other circuits.

The small block marked D-, D+, PHI, N, and DG is not part of this power landing. Leave it until the site has a real DG sense or RS485 run.

Two phase line diagram

R phase

R phase and a neutral enter a 2-pole MCB. R leaves that MCB into RS. RL is the red load toward the room, AC, or other circuit on R.

B phase

B phase and a neutral enter a second 2-pole MCB. B leaves that MCB into BS. BL is the blue load. On the diagram this conductor is blue, even where the MCB input is drawn in red as the live entering the breaker.

Neutral

Join the incoming neutrals at NS, labelled Neutral Wire Source. NL, labelled Neutral Wire Load, continues with the loads to the room, the AC, or the other circuits on this meter.

R and B still need their own neutral path through each MCB. Do not skip the neutral pole because the phases already have a colour.

The terminals you do not use

YS and YL are terminals 3 and 4. The diagram puts a cross through them. No conductor goes there. Do not park a spare wire under those screws.

After the cover is on

Restore the supply. The display should light. Pair WiFi from the Qube app and confirm the meter is online on the dashboard. If one phase reads and the other does not, switch off again and check that phase's source and load only. Do not move a wire onto Y to "complete" the meter.

One circuit on one phase belongs on the single phase installation guide. R, Y, and B together belong on the three phase installation guide.

Frequently asked questions

When is a meter two phase rather than three phase?

Use the two-phase diagram when the supply you are metering is R and B only. Y is not brought to this meter. If R, Y, and B are all present, use the three-phase guide.

What does the red cross on YS and YL mean?

Terminals 3 and 4 are unused. Do not land a phase or a neutral under YS or YL. Leaving them empty is the whole instruction.

How are the neutrals shared?

Each phase still enters through its own 2-pole MCB with a neutral. Those neutrals join at NS, Neutral Wire Source. NL, Neutral Wire Load, is the neutral that leaves with the loads.

Can I use this page for a single room on one phase?

No. One room on one phase uses the single-phase meter, with P1, P2, L1, and L2. This page is only for an R and B supply.

More installation guides

All installation guides

Get rid of manually recording & collecting electricity bills of your rental space.

Switch to Qube's Smart, Effortless & Automated Electricity Billing System

Ideal for PGs, hostels, educational institutions, offices, societies, and businesses of any size.

Buy Now